Lightweight partition wall engineering construction technical specification

Light weight partition wall engineering refers to do not need to set partition keel, the partition plate bearing, made of prefabricated or is directly fixed on the building main body structure of partition wall engineering. so in the construction of some of the technical specifications to follow:

1.t he assembly sequence: When there is a door hole, we should began from the mouth of the cave to both sides. When there is no door hole, shall be installed in the order from one end to the other end.

2. Skeleton partition refers to the partition installed on both sides of the keel to form a wall of lightweight partition wall panel.

3. Keel installation should be controlled in a certain degree of deviation, three-dimensional vertical 3 mm, smooth surface 2 mm.

4. Before installation of gypsum board, should be prepared to adopt measures to strengthen the equipment in the pipeline and attached to the partition wall .

5. Shall adopt the self-tapping screws drywall.

6. Peripheral screw spacing should not be greater than 200 mm, the middle section of screw spacing should not be greater than 300 mm, screw and plate on the edge of the distance should be between 10 to 15.

7. installing the drywall should be started in the middle of the plate to the edges until it is fixed.

Above summarizes some of the technical specification the light board wall projects need to master, which is the construction professionals need to master .Thank you for reading